Quick Answer
Multiply the area by the depth in inches and divide by 324 for cubic yards, then by 1.3 for tons. A 20 × 10 ft area 4 in deep needs 2.47 cubic yards, about 3.21 tons of crushed stone before extra.
Embed this calculator
Adjust the size if needed, then copy the code below into your page or blog. The calculator will load in an iframe and stay updated automatically.
Table of Contents
- Crushed Stone Calculator
- Quick Answer
- Related Calculators
- How This Crushed Stone Calculator Works
- How to Use the Crushed Stone Calculator
- Core Formulas
- Key Terms
- Worked Example
- Real-Life Examples
- Bulk vs Bags
- Crushed stone Needed per 100 sq ft
- Choosing the Depth
- What Changes the Amount
- Common Mistakes to Avoid
- Frequently Asked Questions
- References & Sources
How This Crushed Stone Calculator Works
Pick the shape of the area, enter its size in feet and the depth in inches, and the calculator works out the volume in cubic feet and cubic yards, then the weight in tons using a standard conversion factor for crushed stone. Add a percentage for waste and settling, and the price per ton or per bag, and it shows what to order and what it will cost, in bulk or in bags.
Crushed stone is used under patios, paths and sheds and for driveways; the default factor is the one for limestone, and you can switch to base course or gravel. Save each area as a named job, so a whole yard plan with several beds and paths is ready when you call the supplier, and use Compare to set bulk against bagged.
Quick explanation:
- Cubic yards: sq ft × depth in ÷ 324.
- Tons: cubic yards × 1.3 for crushed stone.
- Bags: cubic feet ÷ bag size, rounded up.
How to Use the Crushed Stone Calculator
- Choose the shape and enter the sizes in feet.
- Enter the depth in inches.
- Keep crushed stone as the material, or type your supplier’s tons per cubic yard.
- Add extra, and the price per ton or per bag.
- Press Calculate, then save the area or compare bulk with bags.
Core Formulas
- Rectangle area: length × width
- Circle area: π × diameter² ÷ 4
- L-shape area: first rectangle + second rectangle
- Cubic yards: area × depth (in) ÷ 12 ÷ 27
- Tons: cubic yards × 1.3 (tons per cubic yard for crushed stone)
- With extra: cubic yards × (1 + extra ÷ 100)
Key Terms
- Cubic yard: 27 cubic feet, a 3 × 3 × 3 ft cube.
- Ton: a US short ton of 2,000 lb.
- Conversion factor: tons per cubic yard of a material.
- Extra: added material for waste and settling.
- Bulk: loose material sold by weight or volume.
Worked Example
A 20 × 10 ft area, 4 in deep, with 10% extra.
- Area: 200 sq ft; volume 200 × 4 ÷ 12 = 66.7 cubic feet
- Cubic yards: 66.7 ÷ 27 = 2.47; with 10% extra 2.72
- Tons: 2.72 × 1.3 = 3.53
- In 0.5 cu ft bags: 147 bags
- A 12 ft circle at the same depth: 1.54 cubic yards, 2.00 tons
Real-Life Examples
- 20 × 10 ft at 4 in: 2.72 cubic yards, 3.53 tons with 10% extra.
- 12 ft circle at 4 in: 2.00 tons.
- L-shape 20 × 10 plus 8 × 6 ft: 4.38 tons.
- In 0.5 cu ft bags (20 × 10 ft): 147 bags.
Bulk vs Bags
- Bulk: sold by the ton or cubic yard and delivered by truck.
- Bags: sold by volume, such as 0.5 cubic foot; easy to carry.
- Compare: enter both prices to see the total for each.
Crushed stone Needed per 100 sq ft
| Depth | Cubic yards | Tons |
|---|---|---|
| 1 in | 0.31 | 0.40 |
| 2 in | 0.62 | 0.80 |
| 3 in | 0.93 | 1.20 |
| 4 in | 1.23 | 1.60 |
| 6 in | 1.85 | 2.41 |
| 8 in | 2.47 | 3.21 |
| 12 in | 3.70 | 4.81 |
Choosing the Depth
Layers under paving are usually set by the project plan; follow it, and remember that compacting a layer makes it thinner. Measure the depth you want after the material is spread and settled, and add the extra percentage for the material that works into the soil or base below. On slopes and around edges, measure a few points and use the average. If you buy by the ton, the conversion factor matters as much as the measurements: ask the supplier what their crushed stone weighs per cubic yard and type it in with Other, since sizes, rock types and moisture all change it.
What Changes the Amount
- Depth: going from 2 to 3 inches adds half again as much material.
- Supplier weight: the tons per cubic yard of your crushed stone may differ from the standard.
- Edges and shapes: split odd areas into rectangles and circles.
- Settling and waste: choose an extra percentage that suits the job.
- Bags vs bulk: bags are handy for small areas; compare the cost per cubic yard.
Common Mistakes to Avoid
- Depth in feet. Enter the depth in inches.
- Forgetting the extra. Some material settles or is lost.
- Using one weight for every crushed stone. Ask your supplier.
- Measuring the wrong area. Split odd shapes into simple ones.
- Mixing up cubic yards and tons. Check how your supplier sells.
Frequently Asked Questions
Area × depth in inches ÷ 324 gives cubic yards.
About 1.3 tons by the standard factor used here.
Multiply by tons per cubic yard; 1.3 for crushed stone.
At 4 in deep, about 62 sq ft.
54 bags of 0.5 cubic foot.
Yes. Choose Other and type it.
Not quite; crushed stone is broken by machine. Pick the closest factor or type your supplier’s.
Yes. Save each one by name in this browser.
Yes. Enter both prices, or use Compare: keep as A.
Yes. Choose the currency for the prices.
Rectangle, circle and L-shape.
Yes. Press Print.
Waste and settling; choose your own percent.
US short tons of 2,000 lb.
References & Sources
| Source | Used For | Link |
|---|---|---|
| New Mexico EMNRD, Conversion Factors for Construction Materials and Common Minerals | Tons per cubic yard: gravel 1/4 to 2 in 1.42, base course 1.25, limestone 1.3, riprap/gabion 1.05, flagstone 1.3, pit run 1.62, scoria/cinders 0.475, sand 1.45 (adapted from BLM Handbook H-3890-1). | https://www.emnrd.nm.gov/mmd/wp-content/uploads/sites/5/ConvFctrs.pdf |